Installing a Monitored Power Supply
The TS790/TS900 can be configured to monitor the
519XB power supply unit using the 519FM fault
monitor PCB. The 519FM plugs directly onto the
519XB PCB plug labelled JP1.
The 519FM PCB monitors any combination of:
l
Supply Failure (mains)
l
Low Battery Voltage
l
12V Failure (fuse failure)
In order to monitor the above fault conditions, the
outputs on the 519FM must be connected to a
detection circuit.
If required, the PSU battery can be “load tested”
periodically by connecting a switched +ve output
to the 519FM BATT TEST terminal. The battery test
occurs every hour on the hour for one minute, if
during this time the battery voltage drops below
10.6V a “Battery Fault” indication will be
generated.
Pre Power-Up Checks
Once the system is installed, but prior to
powering-up give the system one final check to
ensure that:
1. The wiring conforms to the requirements
detailed in this manual and that all
interconnections are correct (A to A, B to B
etc.).
2. All system cables are kept clear of mains
supply cables, telephone cables and R.F.
cables. It is recommended that cable ties be
used to keep cables separated.
3. Verify that maximum cable lengths and
resistances are not exceeded.
4. Mains power supply cables to the system are
connected to an un-switched fused spur.
5. Grommets are used where cables enter metal
housings to ensure that insulation is not
compromised.
Initial Power-Up
To power the system for the first time:
1. Place a small screwdriver blade between the
pins on the control panel PCB, marked
“FACTORY RESET”. This will ensure the factory
default parameters are set, see page 19.
2. Switch on the 240V mains supply and remove
the screwdriver blade.
3. Check that the power LED on the control panel
PCB is illuminated.
4. Check that the LED remote keypads display
“LT” (Panel Lid tamper) and LCD remote
keypads display “Panel Lid tamper”. The
remote keypad sounders and extension
loudspeakers will operate.
5. Enter the engineers passcode (default 1234)
to silence the sounders.
6. Connect the standby battery.
18
System Installation TS790 & TS900 Installation Manual
PSU. Power
PSU. Batt
PSU. Fuse
Supply
Fail
Battery
Low
12V
Fail
Batt Test
0V
Aux 0V
O/P
A+
TC
TB
TA
ZC
ZB
ZA
CIRCUIT C
CIRCUIT B
CIRCUIT A
Battery Test (045)
Program As:-
NODE
519 FM
Figure 24 519FM Connections